Development of a 3-Storey Shop Office in Penang, Malaysia

Connectivity that Catalyzes Success

Fronting the high-traffic along Jalan Permatang Damar Laut

Stage 1

Description

The project officially commenced with piling works and foundation laying, followed by the successful construction of the first storey.

Through systematic planning from day one, we established an efficient operational workflow to ensure the project proceeded smoothly and on schedule.

  • February 2024 – Groundbreaking
  • March 2024 –  Piling Works

Stage 1

Description

  • Mesh work on Ground Floor
  • Cement work on Ground Floor
  • Pillars up on Ground Floor
  • Ceiling up on Ground Floor

August 2024 –  Completion of Ground Floor

Stage 2

Description

Construction progressed steadily with the full structural completion of the first floor. 

Close coordination with our contractors and strong execution management allowed us to hit this structural milestone ahead of schedule, ensuring total alignment with our delivery targets.

  • October 2024 –  Completion of First Floor
  • January 2025 –  Completion of Second Floor

Stage 3

Description

The development reached full completion with final painting and architectural finishing. 

  • Internal Floor Work
  • Internal Wall Skim Coating and Painting
  • Ceiling Waterproof Check
  • Water Pipe Pressure Check and Testing

January – September 2025 

  • External Painting Work
  • Compliance

Stage 3

Description

  • External wall painting
  • External wall paint work done
  • Fire extinguishers for every unit
  • Underground water pipe thickness measured by PBA

January – September 2025  

  •    External Painting Work
  •    Compliance

Stage 4

Description

We are pleased to report the successful completion of the project, achieving the Certificate of Practical Completion (CPC) in February 2026 (Month 22) and the full Certificate of Completion and Compliance (CCC) in April 2026, meeting our 25-month total timeline.